EUDR · 2023/111530.12.2026 — 71 days
EUDRcheck

EUDR and free zones: do re-exports change your duties?

No, not while goods stay there. EUDR obligations turn on release for free circulation, not physical presence in a free zone, warehouse or in transit.

8 min read5 primary sources
On this page
  1. 01What actually switches EUDR obligations on
  2. 02Re-export: leaving without ever arriving, in customs terms
  3. 03Transhipment and transit: moving goods without releasing them
  4. 04When does a free-zone shipment become an EUDR matter?
  5. 05A worked example: palm oil through a Rotterdam free zone
  6. 06Re-importing after a spell in a free zone
  7. 07Table: customs procedure and EUDR status
  8. 08What a freight forwarder or free-zone operator should actually do
  9. 09What is still unsettled

No. A relevant product sitting in an EU free zone, a customs warehouse, under transit, or moving straight back out again without ever clearing customs for the EU market, is outside the EUDR at that stage. The regulation is triggered by the customs procedure called release for free circulation, not by a vessel docking, a container being craned onto another ship, or stock sitting in a bonded shed. Transhipment on its own changes nothing.

What actually switches EUDR obligations on

The Commission's guidance document on the regulation is explicit about the trigger. A relevant product is only treated as placed on the EU market once it has both been brought into the customs territory of the Union and declared under the customs procedure release for free circulation. Everything else — customs warehousing, inward processing, temporary admission, transit, and the free zone procedure itself — sits outside that definition. The guidance lists these procedures by name as not within the scope of the EUDR.

That matters because free zones, bonded warehouses and transit corridors exist precisely so that non-Union goods can move, be stored, be repacked, or be transhipped onto another vessel or lorry without acquiring Union goods status and without the duties, VAT and import charges that come with release for free circulation. The EUDR rides on top of that same customs architecture. If the goods have not cleared into free circulation, they have not, in the regulation's own terms, been placed on the EU market — and no due diligence statement is owed for that movement.

Re-export: leaving without ever arriving, in customs terms

Article 270 of the Union Customs Code lets non-Union goods leave the customs territory again — as a straight re-export, or after a spell in a free zone or warehouse — without having gone through release for free circulation. The Commission's EUDR guidance says this kind of re-export is, for that reason, not within the scope of the regulation: the product never acquired Union goods status in the first place, so there is nothing for the EUDR's placing-on-the-market obligation to attach to.

That is a narrower exemption than it can sound. It only covers genuine re-export of non-Union goods that stayed outside free circulation the whole time they were in the EU. A product that is released for free circulation, briefly enters EU commerce, and is then exported again is a different case: that first release is what triggers the due diligence statement, and the subsequent export is covered separately under the regulation's export rules (see how to submit a due diligence statement in TRACES for how the reference number then has to appear in the export declaration).

Transhipment and transit: moving goods without releasing them

Transhipment — unloading a container from one vessel and loading it onto another, often without leaving the port — is ordinarily done under a transit or free zone procedure precisely so that duties are not triggered twice. Because transit is one of the customs procedures the Commission's guidance names as outside the EUDR's placing-on-the-market trigger, a container that is transhipped through an EU port en route to a non-EU destination does not, by itself, create an EUDR obligation for anyone in that chain, provided it genuinely never enters free circulation.

The practical risk is not the rule — it is proving which side of the line a specific shipment landed on. A shipment that was meant to transit but ends up partially released, split, or redirected into EU distribution has crossed into EUDR scope the moment that declaration is made, whatever the original shipping plan said.

When does a free-zone shipment become an EUDR matter?

The moment it does: as soon as any part of a consignment held in a free zone, warehouse or under transit is declared for release for free circulation with the intention of supplying the EU market, the operator making that declaration takes on the full due diligence obligation for that part, exactly as if the goods had arrived directly. Time spent in the free zone beforehand does not reduce or simplify what follows — there is no partial or discounted due diligence for goods that took a detour through bonded storage first.

Who that operator is depends on who is named on the customs declaration at the point of release, and on whether the regulation's obligations already fell on someone earlier in the chain (see who still owes a due diligence statement once goods are downstream). A business operating only within the free zone — a warehouse keeper or terminal operator handling goods that are never released for free circulation on its own account — is not the one making that declaration and does not itself become an EUDR operator by virtue of handling the goods.

A worked example: palm oil through a Rotterdam free zone

Take a trader buying crude palm oil from Indonesia, routing it through a free zone at Rotterdam, and selling part of the cargo on to a buyer in the United Kingdom while releasing the rest for sale within the EU. The portion that goes on to the UK can move under the free zone procedure and then re-export under Article 270 of the Union Customs Code without ever being released for free circulation — that portion sits outside the EUDR throughout, and no due diligence statement is needed for it.

The portion sold into the EU is a different transaction entirely, even though it travelled in the same container and sat in the same shed. The moment that portion is declared for release for free circulation, the trader making that declaration becomes the operator placing a relevant product on the EU market for the first time, with the full Article 8 due diligence obligation — risk assessment, geolocation back to the plantations, the lot — attaching to that portion only. Splitting a single cargo this way is routine in commodity trading, and it means two parts of the same shipment can have entirely different EUDR status depending on which customs procedure each part is actually declared under, not on where the ship docked or how the cargo was described when it left origin.

Re-importing after a spell in a free zone

A related case is goods that were released for free circulation in the EU, then moved out again — to a free zone for storage or onward sale, or genuinely exported — and later brought back in. The Commission's guidance and national customs authorities treat the person handling that re-entry as a downstream operator, not as the operator placing the product on the market for the first time, provided the product can be shown to have already cleared release for free circulation once before. In practice that means producing the original customs declaration, contract or invoice, and citing the original due diligence statement's reference number (or, where that cannot be traced, the universal reference number the Commission publishes for products placed on the market during the transitional period). Guidance from the Commission on some of the finer points of re-importation is still awaited, so treat this as the current position rather than a closed question, particularly where the original release happened long enough ago that the paperwork has gone astray.

Table: customs procedure and EUDR status

Customs procedure Union goods status gained EUDR obligation at that stage
Release for free circulation Yes Triggers due diligence statement (or reference number, if downstream)
Customs warehousing No None
Free zone procedure No None
Inward processing No None
Temporary admission No None
External/internal transit No None
Re-export under Article 270 UCC No (goods never gained it) None
Export (Union goods leaving the EU) N/A — already Union goods Reference number or declaration identifier required in the export declaration

What a freight forwarder or free-zone operator should actually do

None of this removes the practical burden of knowing where a consignment sits in that table at any given moment, and proving it later if a competent authority asks. In practice that means:

  • Keep the customs declarations showing which procedure the goods were under at each stage — warehousing, free zone, transit, then release for free circulation or re-export. These are the documents that establish you were, or were not, the one who triggered the obligation (see what EUDR records you must keep and for how long).
  • Do not assume a client's instruction to "just tranship" settles the question. If the final declaration ends up being release for free circulation rather than re-export or transit, the EUDR obligation attaches at that point regardless of what was originally planned.
  • If you are a non-EU business arranging the release yourself — rather than through an EU-based importer — check whether you need an EU-based authorised representative to act for you (see EUDR authorised representative: when a non-EU business actually needs one).
  • Where the free-zone leg is only one stage of a longer UK-to-EU or third-country-to-EU route, the obligation still lands on whoever declares release for free circulation into the EU market, UK-based or not (see EUDR for UK businesses selling into the EU).

If your business is not sure whether the goods it handles are ever actually released for free circulation, or who in the chain that falls to, check what EUDR requires of your specific business rather than assuming the free-zone leg takes you out of scope altogether.

What is still unsettled

The Commission's guidance document states the customs-procedure trigger clearly, but it does not use the words "free zone" when discussing re-export and transhipment specifically — it addresses free zones only through the general customs-procedure list and through Article 270 of the Union Customs Code. There is no EUDR-specific free-zone guidance beyond that general rule, and no published Commission FAQ answer we could find that works through a transhipment scenario end to end. Where a free-zone movement is unusual — split consignments, partial release, or goods changing ownership while in the zone — treat the general rule as the starting point and check with the relevant competent authority or a customs specialist before relying on it for a specific shipment.

General information about Regulation (EU) 2023/1115 as amended, not legal advice. EUDR scope is determined by customs (CN) code — confirm your own classifications before acting on this. Checked against primary sources on .

Questions

Frequently asked

01Does the EUDR apply to goods that are only transhipped through an EU port?

Not on its own. Transhipment is normally carried out under transit or the free zone procedure, which the Commission's EUDR guidance lists as outside the regulation's placing-on-the-market trigger. The goods would need to be declared for release for free circulation before any EUDR obligation arose.

02Do I need a due diligence statement for goods held in an EU free zone?

No, not while they stay under the free zone procedure. A due diligence statement is only required once the goods are declared for release for free circulation with the intention of supplying the EU market, or exported as Union goods.

03Is re-exporting from a free zone the same as re-exporting goods that already entered the EU market?

No. Re-export under Article 270 of the Union Customs Code covers goods that never acquired Union goods status, so the EUDR does not apply to that movement. Goods that were released for free circulation first, then exported again, are a different case — the original release already triggered a due diligence statement, and the export has its own reference-number requirement.

04Who is responsible for EUDR compliance if goods pass through several warehouses and a free zone before reaching the EU market?

The obligation falls on whoever is named on the customs declaration at the point the goods are declared for release for free circulation, not on anyone who only stored, warehoused or transhipped them beforehand without releasing them.

05Does a warehouse or terminal operator become an EUDR operator by handling relevant products in a free zone?

Not by that alone. Handling goods under customs warehousing, inward processing, temporary admission, transit or the free zone procedure does not make the handler an EUDR operator. The obligation attaches to whoever declares the goods for release for free circulation on their own account.

06Can goods lose their free-zone status partway through and trigger an EUDR obligation unexpectedly?

Yes. If any part of a consignment is declared for release for free circulation instead of continuing in transit or re-export, that declaration triggers the obligation at that point, whatever the shipment was originally planned to do.

07Where does the Commission state that free zones and transit fall outside the EUDR?

The Commission's 2026 Guidance Document for the Regulation on Deforestation-Free Products lists customs warehousing, inward processing, temporary admission and transit by name as customs procedures that are not within the scope of the EUDR, and treats re-export under Article 270 of the Union Customs Code the same way. It does not use the words "free zone" when making that specific point, so free-zone-specific scenarios should be checked against the general rule rather than a dedicated passage.

References

Sources

  1. [1]Guidance Document for the Regulation on Deforestation-Free Products (2026)
  2. [2]Regulation (EU) 2023/1115 (EUR-Lex)
  3. [3]Regulation (EU) No 952/2013 — Union Customs Code (EUR-Lex)
  4. [4]Council: targeted revision to simplify and postpone the deforestation regulation
  5. [5]Ruokavirasto — EUDR in imports and exports
Keep reading